East Windsor Rd update!  PLEASE BE PREPARED FOR DELAYS WHILE COMMUTING THROUGH THE AREA DURING CONSTRUCTION!

East Windsor Rd update! Construction on East Windsor Rd from North Rd to the Windsor town line is set to begin by the last week of August or the first week of September. All State Materials Group will begin full depth reclaiming of the road surface along with adding 2,000 ton of 1.5” dense grade and liquid calcium / mile to the gravel base. Reclaiming is expected to last up to 2 weeks. Once the reclaiming and reshaping of the road is completed, LB Corporation will start paving the road. First with 2.5” of a binder layer and followed by 1.5” of a top course layer. All intersections with gravel roads will be paved and all driveways will have new black top aprons installed. In addition to the paving there will be ¾” dense grade added to the entire length of the road on the shoulders. Paving is expected to last 2 to 3 weeks.
PLEASE BE PREPARED FOR DELAYS WHILE COMMUTING THROUGH THE AREA DURING CONSTRUCTION!

 

Justin Russell , Highway Superintendent